MAY 24: Piers & footings layed ...
The last two weeks has been a mixed blessing for us. While the arrival of the rain this week has been welcomed by the farm it hasn't been made so welcome by building project! Work carried out over these two weeks includes the laying footings and bricks for the reception building and working on plumbing and electrical upstairs. Scheduled piering for the conference building has been delayed due to the rain.
Piers drilled for the new reception building ...
'Footings' prepared for the cement pour ...
Cement pour underway ...
Brick supports layed for the reception slab ...
A new grease arrester (trap!) installed at the back of the kitchen ...
Some of the stormwater and sewer plumbing layed ...
The last of the new openings is made in preparation for the new bedrooms ...
The raised verandah almost complete ....
The kitchen ceiling is removed to provide access for bathroom plumbing above ...

The conference hall site stalled for a few days due to rain ...

The architect and builders sign off on the 'door furniture' to be installed ...
Br Charlie clears the Shelter Shed of it mountain of autumn leaves ...